Global Microturbine - Global Energy LLC


Publication Title | RULE 21 INTERCONNECTION STANDARDS FOR NON-UTILITY OWNED GENERATION

Microturbine Search Engine Series

Capstone Turbine Publications search was updated real-time via Filemaker on:

Capstone Turbine Publications | Return to Search List

Search Completed | Title | RULE 21 INTERCONNECTION STANDARDS FOR NON-UTILITY OWNED GENERATION
Original File Name Searched: california05.pdf | Google It | Yahoo | Bing



Page Number: 001
Previous Page View | Next Page View

Text | RULE 21 INTERCONNECTION STANDARDS FOR NON-UTILITY OWNED GENERATION | 001



Original Cal.P.U.C.SheetNo. Cal. P.U.C. Sheet No.

14111-E

San Diego Gas & Electric Company San Diego, California

Canceling

RULE 21

INTERCONNECTION STANDARDS FOR NON-UTILITY OWNED GENERATION

A. APPLICABILITY AND INTRODUCTION

Sheet 1

1. Applicability. This Rule describes the interconnection, operating and metering requirements for Generating Facilities that are intended to be connected to the Distribution System over which the California Public Utilities Commission (CPUC) has jurisdiction. Subject to the requirements of this Rule, San Diego Gas & Electric (SDG&E) will allow the interconnection of Generating Facilities with its Distribution System.

2. Definitions. Capitalized terms used in this Rule, and not otherwise defined, shall have the meaning ascribed to such terms in Section H.

3. Enabling Documents. It is contemplated that the Applicant will be required to execute various enabling documents, such as the Application and Interconnection Agreement. Such documents shall be in the form on file with the CPUC, as may be amended from time to time.

B. GENERAL RULES, RIGHTS AND OBLIGATIONS

1. Authorization Required to Interconnect. An Electricity Producer must comply with this Rule, form an Interconnection Agreement with SDG&E, and receive SDG&E’s express written permission to interconnect before connecting or operating a Generating Facility in parallel with SDG&E’s Distribution System. SDG&E shall apply this Rule in a non-discriminatory manner and shall not unreasonably withhold its permission to interconnect an Electric Producer’s Generating Facility.

2. Separate Arrangements Required for Other Services. An Electricity Producer requiring other electric services from SDG&E including, but not limited to, Distribution Service provided by SDG&E during periods of curtailment or interruption of a Generating Facility, must enter into separate arrangements with SDG&E for such services in accordance with CPUC-approved tariffs.

3. Transmission Service Not Provided with Interconnection. Interconnection with SDG&E's Distribution System under this Rule does not provide an Electricity Producer any rights to utilize SDG&E's Distribution System for the transmission or distribution of electric power, nor does it limit those rights.

4. Compliance with Laws, Rules, and Tariffs. An Electricity Producer shall ascertain and comply with applicable CPUC-approved rules, tariffs, and regulations of SDG&E; applicable FERC-approved rules, tariffs, and regulations; and any local, state or federal law, statute or regulation which applies to the design, siting, construction, installation, operation, or any other aspect of the Electricity Producer’s Generating Facility and Interconnection Facilities.

(Continued)

Advice Ltr. No. 1283-E Decision No. 00-12-037

Issued by

William L. Reed

Vice President Chief Regulatory Officer

Date Filed Effective

Resolution No.

January 5, 2001 January 5, 2001

Image | RULE 21 INTERCONNECTION STANDARDS FOR NON-UTILITY OWNED GENERATION



rule-21-interconnection-standards-for-non-utility-owned-generation
Capstone Turbine For Sale - Microturbine C30 C65 C200 C600 C800 C1000 - Go to microturbine website

Search Engine Contact: greg@globalmicroturbine.com